
Services
Independent third-party commissioning agent for the owner across the project.
Day-to-day management of the full commissioning programme on the client's behalf.
Embedded in the main contractor's MEP team, delivering their Cx scope to the end client's standard.
Most commissioning problems sit at the interfaces: between pieces of equipment, between commissioning levels and between each party's scope. Keeping the same team on the project bridges those interfaces and closes the gaps where most problems start.
Whether we work for the end client or the contractor, our method stays the same: deliver the project to the owner's requirements.
We review the OPR, basis of design, equipment specifications, submittals and sequences of operation against how the facility will actually run. An error found here costs a markup. Found at L4 or L5, it costs a retest and sometimes a date.
We witness factory acceptance tests on critical equipment: generators, MV and LV switchgear, UPS, cooling plant and controls. A fault found at the factory is fixed by the manufacturer on their own floor, away from the site programme.
Installation inspections, point-to-point checks and pre-energisation QC. Construction quality is documented and signed before energisation, so L3 starts from a known baseline. At every check we ask ourselves, "Is this safe to energise?"
Each asset is energised and started under controlled conditions, with the vendor start-up and pre-functional checks completed and recorded. This is where we see real potential to de-risk a commissioning programme. A tightly coordinated and engaged L3 can seriously reduce the issues and delays at L4 and L5.
System-level testing through start-up, normal operation, alarm response and fault scenarios. Most defects show up here, and so does schedule risk. We write the scripts, witness the tests and track every issue to close-out.
Power, cooling, controls and life-safety systems tested together under simulated and real load. We cut the utility supply and deliberately fail equipment down to N. Then we verify that power transfers, cooling holds, alarms reach the right people and the IT load stays within limits, and that the site recovers in the correct sequence. If the design says the site can lose any single component without losing load, IST is where we prove it.
Test results, deviations, sign-offs, as-left drawings, training and O&M documentation, put together with the team that will run the building. Where required, we package the commissioning record to support LEED credits.
Data centres first.
Hyperscale and colocation data centres are our focus. We also take on other mission-critical work where commissioning decides how the facility performs, mainly energy infrastructure and industrial plant.